25 September 2018

September 2018

There was a lot of great news on the Ecosphere Metropolis construction site in September.
Here is the detailed description of the status of construction work:


House number 1

The installation of the vertical constructions of the monolithic frame is over on the 16th floor.
The bricklaying proceeds to7-8th floors.

House 2 section 1
The monolithic frame installation is totally completed!
The bricklaying proceeds to7-8-9th floors.

House 2 section 2
The installation of the vertical constructions of the monolithic frame is over on the 10th floor
The bricklaying proceeds to 2-4th floors.

 