Progress building news

  • Construction progress for February 2019

    House number 1 Finished work on the device monolithic frame on the 22nd floor Carry out masonry work from the 16th to the 19th floor Works on the installation of precast concrete structures (staircases) on the 22nd floor were completed.

  • December 2018

    The monolithic frame is being arranged on the 22th floor. We proceed masonry work on the 10-17 th floors. The concrete-steel constructions (stair flights) are installed from 17th to 20th floors

  • November 2018

    The fall comes to an end and we are ready to welcome winter with good news from Metropolis Ecosphere

  • October 2018

    We’ve made great job in October in order to proudly present to you the status of completed construction works in the Metropolis Ecosphere

  • September 2018

    There was a lot of great news on the Ecosphere Metropolis construction site in September. Here is the detailed description of the status of construction work

  • August 2018

    The August shows us great results of the building process on the construction site of Metropolis Ecosphere. You may find the detailed status here

  • July 2018

    The preparation works for the vertical constructions installation on the 11th floor. The bricks are layed on the 5th floor.

  • June 2018

    The vertical constructions installation on the 7th floor is on its final stage. We are also installing the flooring panel on this floor. The bricklaying process on the 2nd floor has begun.

  • May 2018

    The flooring panel is being installed on the 5th floor. And the vertical constructions installation on the 6th floor.

  • April 2018

    The vertical constructions are installed on the 4th floor.

  • March 2018

    House 1. The part of the flooring panel of the 2nd floor is installed. The waterproofing finishing is completed. The preparation for the soil backfilling process.

  • February 2018

    House 1. The flooring panel is installed on the level +0.000 (half of the ground floor). The vertical constructions installation process on the 1st floor.

  • January 2018

    House 1 The monolithic works of the vertical structures of the basement are finalizing. The monolithic works of the flooring installation on the level 0.000 are made.

  • December 2017

    The foundation panel of the House 1 is installed. The vertical constructions installation on the -1st floor on the level (-3.300) has begun.

  • November 2017

    During October and November at the construction site of the Metropolis, a set of works was carried out in the field of the planning of soil masses and compaction of the foundation pit.

  • October 2017

    The tower crane is installed. The pile field is arranged. Preparatory work on the foundation plate is being carried out.