25 December 2018

December 2018

House 1
The monolithic frame is being arranged on the 22th floor.
We proceed masonry work on the 10-17 th floors. 
The concrete-steel constructions (stair flights) are installed from 17th to 20th floors.

House 2

Section 1
We are finalizing the masonry work from 10th to 17th floors.
Windows installation is finished up to2 floor.
Section 2
The monolithic frame is being arranged on the 18th floor
We proceed masonry work from 6th to 9th floors. 
The concrete-steel constructions (stair flights) have been installed on the 15th floor.

House 3
Section 3.1.

Piles testing is already finished


Section 3.2
The installation of pile field is accomplished.
The arrangement of the mattress is in process.


Section 3.3
The mattress is being armoured.

/