25 December 2017

December 2017

The foundation panel of the House 1 is installed. The vertical constructions installation on the -1st floor on the level (-3.300) has begun.

House 2 section 1

The pale field arrangement works are completed. And the pales for crane foundation installed.

House 2 section 2

The pale field arrangement works and foundation mats are completed.

The horizontal waterproofing works has begun.

 