25 June 2018

June 2018

House 1

The vertical constructions installation on the 7th floor is on its final stage.

We are also installing the flooring panel on this floor.

The bricklaying process on the 2nd floor has begun.

 

House 2 section 1

We are installing the flooring panel on the 6th floor.

The vertical constructions installation on the 7th floor are in process.

The masonry works are provided on the 2-3d floors. 

 

House 2 section 2

The vertical constructions installation is on the 4th floor and the bricklaying – on the 2nd.